West Campus ADA Upgrades
The West Entrance to campus was identified as an area where better ADA access and student drop-off safety was necessary.
This project eliminates all stairs and ADA accessibility obstacles at the West Entrance. By removing the entry stairs from the west side of the library and the granite wall, the College will install a gradual walking path that is ADA acceptable. An upgrade to the Library Patio is included in this project and will increase access to the Library.
Construction for the exterior renovation is projected for completion in Fall 2021.
Jump to Month
Project Updates
October 2022
Past Month’s Accomplishments: 11-month warranty walk was completed.
Next Month’s Milestones: The project is complete.
September 2022
Past Month’s Accomplishments: All close out documents were completed, and DSA project certification was received.
Next Month’s Milestones: An 11-month warranty walk will be coordinated. A Notice of Completion will be presented to the September Board for approval and will be filed with Santa Clara County after board approval.
August 2022
Past Month’s Accomplishments: All close out documents were completed. DSA project certification was received.
Next Month’s Milestones: A Notice of Completion will be submitted for September Board approval and will be filed with Santa Clara County after approval. An 11-month warranty walk will be coordinated.
July 2022
Past Month’s Accomplishments: The final walk with M&O and Electrical Engineers (SOBE) for site acceptance was completed. Furniture installation was also completed.
Next Month’s Milestones: Final punch list items will be completed, and contract close-out will commence. A draft Notice of Completion will be sent to the August Board.
June 2022
Past Month’s Accomplishments: The final walk with M&O and Electrical Engineers (SOBE) for site acceptance was completed. Furniture installation was also completed.
Next Month’s Milestones: Final punch list items will be completed, and contract close-out will commence. A draft Notice of Completion will be sent to the August Board.
May 2022
Past Month’s Accomplishments: Repairs are ongoing per the final punchlist. Fencing removal was completed. Furniture installation in the plaza areas was completed.
Next Month’s Milestones: A final walk with the project engineers will take place. Training for water fountains and programming for electrical will take place. The contract will be closed out and a Notice of Completion to the Board will be drafted.
April 2022
Past Month’s Accomplishments: Bench lighting and lighting controls motor inside Cedro Plaza were replaced. Repairs are ongoing per final punch list.
Next Month’s Milestones: A final walk with the District by M&O will occur. The contract will be closed out.
March 2022
Past Month’s Accomplishments: Replacement of bench lighting and lighting controls motor inside Cedro Plaza completed. Repairs ongoing per final punch list. Flat work repair ongoing.
Next Month’s Milestones: A final walk with the District and M&O and contract close-out to occur.
February 2022
Past Month’s Accomplishments: Replacement of bench lighting and the lighting controls motor inside Cedro Plaza was completed. Repairs continued per the final punch list. Flat work repairs continued.
Next Month’s Milestones: A final walk with the District and M&O will take place. Contract close-out will commence.
January 2022
Past Month’s Accomplishments: Non-compliant flatwork based on an ADA report provided by DASP Consultant and Project Inspector was repaired. Punch list repairs continued.
Next Month’s Milestones: Training for pathway lighting programming will be carried out. Contract close-out will commence.
December 2021
Past Month’s Accomplishments: Final clean up and demobilization were completed. Training for pathway lighting programming was carried out. Contract close-out is underway.
Next Month’s Milestones: Contract close-out will be completed.
November 2021
Past Month’s Accomplishments: Repairs of non-compliant flatwork based on ADA report provided by DASP Consultant and Project Inspector were completed. Punch list repairs were continued, and the final punch list was issued by the project architect. Installation of the base contract Electrical Scope of Work was completed. Installation of furniture approved by the College was finalized.
Next Month’s Milestones: The final clean-up and demobilization will be carried out, along with training for pathway lighting programming and contract close-out.
October 2021
Past Month’s Accomplishments: Non-compliant flatwork was repaired based on an ADA report provided by DASP Consultant and Project Inspector. Punch list repair items were continued. Installation of base contract for Electrical Scope of Work was completed. Installation of furniture approved by the College was finalized. The final punch list was issued by the project architect.
Next Month’s Milestones: Final cleanup and demobilization will be carried out, as well as training for pathway lighting programming. The contract will then be closed out.
September 2021
Past Month’s Accomplishments: Landscape irrigation restoration, site concrete, and Cedro Plaza planting were all completed.
Next Month’s Milestones: The ACI inspector survey on the flatwork installation will be completed. Lighting installation and punch list repair work will also be completed. A final cleanup will be carried out followed by demobilization.
August 2021
Past Month’s Accomplishments: 95% of site concrete was installed. Site furnishings were laid out. Salvaged granite benches were placed and installed. Landscape irrigation restoration was also completed.
Next Month’s Milestones: ACI Inspector will be onsite to survey flatwork installation. Planting inside Cedro Plaza and patch repair of the seat wall will be completed. Installation of lighting in Cedro Plaza will be completed. Box panels will be installed. Final clean up and demobilization will also be completed.
July 2021
Past Month’s Accomplishments: ADA Pathway concrete was completed with logos. Light poles were installed and tested. Site furnishings layout is underway. Granite benches were placed. Pavers and lighting and logo in roadway landscaping prep are underway. Finally, shade structures were complete and installed.
Next Month’s Milestones: Roadway concrete and parking lot striping will be finalized and completed. Cedro Plaza –logos, concrete, site furnishings, pavers and electrical- will be completed, as will the water fountain system in LETC Plaza. Finally, the site will be restored.
June 2021
Past Month’s Accomplishments: EVC Sign was installed outside LETC. Water fountain utilities were completed, and concrete was poured. Logos were prepped for lithocrete. Traffic rated and non-traffic rated bollards were installed at 90%.
Next Month’s Milestones: The remainder of the colored concrete installation will be completed. Tile around water fountain will be installed and plumbing and lighting will be tested. Installation of pavers and electrical fixtures inside LETC and Cedro Plaza will also be completed.
May 2021
Past Month’s Accomplishments: CM rejected 30% of poured Harvest Gold concrete outside of LETC plaza. Kalua was poured and pending cure time for assessment in ADA Pathway. Review of Schedule delays are underway. Impacts to Cedro Elevations based on existing conditions vs. Topo was provided by U&R. Conflict with existing water line was shown in 2016 utility map. Hot tap required at nearest hydrant. Closeout is forthcoming for this work.
Next Month’s Milestones: Installation of Lithocrete logos, pavers, Bollards, Light Poles, USA Shade Structure, remainder of Colored Concrete and Furniture.
April 2021
Past Month’s Accomplishments: Harvest Gold concrete poured in a pathway at the LETC patio. Integral colors for bands form work complete. The contractor is preparing underground utilities for lighting and plumbing related to the fountain replacement.
Next Month’s Milestones: The Bond Team expects to review a Lithocrete mock-up, EVC logo pavers, and additional integral concrete color mock-ups.
Construction Updates: The current and upcoming work items include the following:
Ongoing soil compaction and installation of new drain in Cedro Plaza. Formwork
underway.
Ongoing concrete formwork, rebar, and colored concrete pours in Library Plaza and
pathway.
Ongoing installation of the base for the illuminate traffic bollards. Concrete pour for
bollard underway.
Ongoing water connection, forming, and rebar the fountain in the Library Plaza.
Approved lithocrete and unit paver mockup.
March 2021
Past Month’s Accomplishments: Pour concrete outside of LETC. Continuation of forming. Preparation of underground utilities – lighting and plumbing for fountain.
Next Month’s Milestones: Continue with site concrete outside LETC and Cedro Plaza. Rough-in for monument sign and shade structures. Evaluation of schedule impacts from GC.
February 2021
Past Month’s Accomplishments: Site demolition is complete. Rough grade is 95% complete. Site prep, area drains and trenching for underground are roughly 50% complete.
Next Month’s Milestones: Concrete samples for review. Underground utilities. GC to provide progress schedule update.
January 2021
Past Month’s Accomplishments: Site demolition is roughly 90% complete. Rough grade, site prep, area drains and trenching underway.
Next Month’s Milestones: Added scope per College Ground's request to remove and install seven new trees along Cedro pathway. Existing trees have fungus and is spreading into roots of neighbor tree.
December 2020
Past Month’s Accomplishments: Team held pre-construction kick off with D.L. Falk OCIP rep. GC mobilized fence on 12/1/2020. Contractor started removal of finishes identified to be salvaged and repurposed on Campus.
EVC Logo Signage: DSA provided back check comments. Disapproved revision. Now working on revision #3 with Ad Art and Perkins Eastman.
Next Month’s Milestones: Complete mobilization, utility survey, and safe off-site electrical for new work related to light poles and ground lighting.
EVC Logo Signage: Resubmit to DSA before end of year.
November 2020
Past Month’s Accomplishments: Notice to Proceed issued to DL Falk Construction. Contract value $2,344,000. This is an OCIP & PLA Project.
EVC Logo Signage: Shop drawings and Structural Calculations are with Design Architect for review.
Next Month’s Milestones: Mobilization and Kickoff Meeting to start week of 12/1/2020.
EVC Logo Signage: Submittal as a CCD to DSA for approval first week of November by Perkins Eastman.
October 2020
Past Month’s Accomplishments: Project to be awarded to DL Falk at November 17, 2020 Board Meeting.
EVC Logo Signage: Shop drawings and Structural Calculations were submitted to the design architect for review.
Next Month’s Milestones: Mobilization to start in December.
EVC Logo Signage: It is expected that the signage will be submitted as a Construction Change Directive to Division of the State Architect (DSA) for approval in the first week of November by Perkins Eastman.
September 2020
Past Month’s Accomplishments: The project was published for a public bid. The Bond Team held a virtual, Zoom-based, mandatory bid walk. At least eight contractors are looking at the project.
EVC Logo Signage: Shop drawings and structural calculations sent to design architect for review.
Next Month’s Milestones: Bids are due October 15, 2020.
EVC Logo Signage: Submit construction change directive (CCD) to Division of the State Architect (DSA) for approval.