Entry Road and Parking Lots
A new gateway access to the campus is being designed off of Yerba Buena Road.
The entry road will provide a new, potentially signalized, intersection that will allow access into campus from Yerba Buena Road. The first building on the new road will be the new Student Services Complex and new parking lots. The project will also provide a new pedestrian walkway and bike path that is separated from traffic. The new parking lot will replace the storage building and archery field to include approximately the same number of spaces as lots 4 and 5. The existing lots 4 and 5 will be demolished for the new Student Services Complex.
Jump to Month
Project Updates
August 2024
Past Month’s Accomplishments: The off-site punch list was completed. A punch back walk with the City of San Jose was completed.
Next Month’s Milestones: Final completion and sign-off from the City of San Jose are expected.
May 2024
Past Month’s Accomplishments: The off-site punch list was completed.
Next Month’s Milestones: Final completion is expected.
April 2024
Past Month’s Accomplishments: Off-site electrical work was completed.
Next Month’s Milestones: Correction of landscape deficiencies will be completed. Installation of the off-site paving scope will be completed.
March 2024
Past Month’s Accomplishments: Off-site electrical work was completed.
Next Month’s Milestones: Correction of landscape deficiencies will be completed. Installation of the off-site paving scope will be completed.
February 2024
Past Month’s Accomplishments: Off-site electrical work was completed.
Next Month’s Milestones: Correction of landscape deficiencies will be completed. Installation of the off-site paving scope will be completed.
January 2024
Past Month’s Accomplishments: Off-site hardscape and striping work was completed.
Next Month’s Milestones: Correction of landscape deficiencies will be completed. Installation of the off-site electrical scope will be completed.
December 2023
Past Month’s Accomplishments: Off-site hardscape and striping work was completed.
Next Month’s Milestones: Correction of landscape deficiencies will be completed. Installation of the off-site electrical scope will be completed.
November 2023
Past Month’s Accomplishments: Off-site hardscape and striping work was completed.
Next Month’s Milestones: Correction of landscape deficiencies will be completed. Installation of the off-site electrical scope will be completed.
October 2023
Past Month’s Accomplishments: Off-site hardscape and striping work was completed.
Next Month’s Milestones: Correction of landscape deficiencies will be completed. Installation of the off-site electrical scope will be completed.
September 2023
Past Month’s Accomplishments: Off-site hardscape and striping work was completed.
Next Month’s Milestones: Correction of landscape deficiencies will be completed. Installation of the off-site electrical scope will be completed.
August 2023
Past Month’s Accomplishments: Off-site hardscape and striping work was completed.
Next Month’s Milestones: Correction of landscape deficiencies will be completed. Installation of the off-site electrical scope will be completed.
July 2023
Past Month’s Accomplishments: Off-site hardscape and striping work was completed.
Next Month’s Milestones: Correction of landscape deficiencies is expected. Installation of off-site electrical scope will be completed.
June 2023
Past Month’s Accomplishments: Asphalt replacement at the off-site area was completed.
Next Month’s Milestones: Correction of landscape deficiencies will be completed. Installation of off-site electrical scope is expected.
May 2023
Past Month’s Accomplishments: Lot 4/5 replacement was completed. Hardscape installation off-site was completed.
Next Month’s Milestones: Asphalt replacement at the off-site area will begin.
April 2023
Past Month’s Accomplishments: Lot 4/5 replacement and hardscape offsite installation were completed.
Next Month’s Milestones: Asphalt replacement at the offsite area to begin.
March 2023
Past Month’s Accomplishments: Offsite work began.
Next Month’s Milestones: Asphalt replacement will begin.
February 2023
Past Month’s Accomplishments: Asphalt grinding of parking lots was completed. Encroachment permit was acquired.
Next Month’s Milestones: Offsite work and asphalt replacement to begin contingent upon weather.
January 2023
Past Month’s Accomplishments: Asphalt grinding of parking lots was completed. Encroachment permit was acquired.
Next Month’s Milestones: Offsite work and asphalt replacement to begin contingent upon weather.
December 2022
Past Month’s Accomplishments: Asphalt grinding of parking lots was completed. Encroachment permit was acquired.
Next Month’s Milestones: Offsite work and asphalt replacement to begin contingent upon weather.
November 2022
Past Month’s Accomplishments: Asphalt grinding at the parking lots was completed.
Next Month’s Milestones: Offsite work will begin pending encroachment permit. Asphalt replacement contingent upon weather.
October 2022
Past Month’s Accomplishments: The encroachment permit was granted.
Next Month’s Milestones: Offsite work will begin. Asphalt replacement and remediation will be completed.
September 2022
Past Month’s Accomplishments: Asphalt deficiency was confirmed.
Next Month’s Milestones: Encroachment permitting will be received. Offsite work will begin. Asphalt remediation will be completed.
August 2022
Past Month’s Accomplishments: Landscape installation was completed.
Next Month’s Milestones: Encroachment permitting will be completed and offsite work will begin.
July 2022
Past Month’s Accomplishments: Landscape installation was completed.
Next Month’s Milestones: Encroachment permitting will be completed and offsite work will begin.
June 2022
Past Month’s Accomplishments: Paving and flat work installation was completed.
Next Month’s Milestones: Landscaping and electrical installation will be completed.
May 2022
Past Month’s Accomplishments: Paving and flat work installation was completed.
Next Month’s Milestones: Landscaping and electrical installation will be completed.
April 2022
Past Month’s Accomplishments: Concrete curbs and underground utilities were put in place.
Next Month’s Milestones: Paving and flat work installation will be completed.
March 2022
Past Month’s Accomplishments: Underground utility operations continued.
Next Month’s Milestones: Installation of irrigation components to begin.
February 2022
Past Month’s Accomplishments: Site demolition and final grading were completed. Underground utility operations are underway.
Next Month’s Milestones: Civil improvements will continue. Lighting circuits will be installed.
January 2022
Past Month’s Accomplishments: Site demolition was completed. Grading and underground utility operations are underway.
Next Month’s Milestones: Final grading will be completed. Lighting circuits will be installed.
December 2021
Past Month’s Accomplishments: Site protection was established. Mass-excavation began.
Next Month’s Milestones: Site grading will be finalized, and mass-excavation will continue.
November 2021
Past Month’s Accomplishments: Phase 1 was awarded to Galeb Construction for $5.25M. The application process for the Entry Permit with the City of San Jose continued.
Next Month’s Milestones: Clearing and grubbing will continue. Mass excavation will begin.
October 2021
Past Month’s Accomplishments: The construction bid was put out for $6M. The application process for the Entry Permit with the City of San Jose continued.
Next Month’s Milestones: The construction contract will be awarded.
September 2021
Past Month’s Accomplishments: DSA approval was received. The application process for the Entry Permit with the City of San Jose continued.
Next Month’s Milestones: The construction contract will be awarded.
August 2021
Past Month’s Accomplishments: DSA Approval was received. The application process for the Entry Permit with the City of San Jose was continued.
Next Month’s Milestones: The project will be advertised for public bid.
July 2021
Past Month’s Accomplishments: DSA backcheck comments were received. Application for the entry permit with the City of San Jose was continued.
Next Month’s Milestones: DSA Approval. The project will be advertised for public bid.
June 2021
Past Month’s Accomplishments: Submittal to DSA.
Next Month’s Milestones: DSA Approval is expected. Bid will be advertised.
May 2021
Past Month’s Accomplishments: The designer completed construction documents and submitted the design to DSA for approval.
Next Month’s Milestones: DSA review is expected to take three months. The Bond Team will continue coordination with the SSC building contractor, XL Construction. Discussions with City of San Jose regarding turn lanes and construction entrance at Yerba Buena will continue.
April 2021
Past Month’s Accomplishments: The designer completed construction documents and submitted the design to DSA for approval.
Next Month’s Milestones: DSA review is expected to take three months. The Bond Team will continue coordination with the SSC building contractor, XL Construction. Discussion with the City of San Jose regarding turn lanes and construction entrance permits from Yerba Buena will continue.
March 2021
Past Month’s Accomplishments: Concept designs complete. Documents submitted to DSA.
Next Month’s Milestones: DSA review (expected to take 3 months). Coordination with SSC building contractor. Continued discussion with City of San Jose regarding turn lanes from Yerba Buena.
February 2021
Past Month’s Accomplishments: 50% of construction documents complete. DSA Pre-submittal meeting scheduled.
Next Month’s Milestones: DSA Pre-submittal Meeting. DSA Submittal – Week of March 24
January 2021
Past Month’s Accomplishments: Design Development phase started 10/6/2020. Completed 11/30/20. Notice to proceed to construction documents 01/13/21 ahead of schedule.
Next Month’s Milestones: Schedule DSA pre-meeting. Intersection at Yerba Buena will not be signalized.
December 2020
Past Month’s Accomplishments: Design development phase started 10/6/2020 and completed 11/30/20. Construction documents scheduled to start 1/18/21.
Next Month’s Milestones: Schedule DSA pre-meeting. Begin construction documents 1/18/21. City opinion on a signalized intersection is expected from San Jose City's Department of Transportation as early as December.
November 2020
Past Month’s Accomplishments: Design Development (DD) phase started 10/6/2020. Scheduled completion 11/30/20. Additional scope was approved by the Board of Trustees for the left-leg of the new road. Construction coordination between the Student Services Complex design team and the Entry Road design team was started in November.
Next Month’s Milestones: Schedule DSA Pre-Meeting, DD Submittal due 11/30/2020. City opinion on a signalized intersection is expected from San Jose City's Department of Transportation as early as 12/2020.
October 2020
Past Month’s Accomplishments: Completed schematic design (SD) plan review. Notice to Proceed (NTP) issued intoDesign development (DD) phase in October.
Next Month’s Milestones: Schedule Division of the State Architect (DSA) pre-meeting. Submit soil report to California Geological Survey (CGS). Design development (DD) submittal is due in November. An expansion of the scope was approved on this project to include the left-leg of this road to help increase circulation and provide additional routes to parking lots on campus. City opinion on a signalized intersection is expected from San Jose City's Department of Transportation, possibly by early December.
September 2020
Past Month’s Accomplishments: Schematic Design (SD) package submitted on August 31.
Next Month’s Milestones: Cost estimate is due mid-September. Cost reconciliation is targeted for end of September. District’s Schematic Design (SD) planning review to be completed by September 30.