Student Activities Center
Student feedback received during the programming effort for the Student Services Complex identified the need for a Student Activities Center.
This project is investigating the potential renovation of the existing Student Services Building to provide student clubs and student organizations with office space, meeting space, and event space.
This project is on hold pending additional budgetary investigations.
Project Updates
July 2022
Past Month’s Accomplishments: No changes.
Next Month’s Milestones: This project is targeted to recommence in Quarter 2 of 2025 to begin procurement efforts for Acacia Demolition.
June 2022
Past Month’s Accomplishments: No changes.
Next Month’s Milestones: This project is targeted to recommence in Quarter 2 of 2025 to begin procurement efforts for Acacia Demolition.
May 2022
Past Month’s Accomplishments: No changes.
Next Month’s Milestones: This project is targeted to recommence in Quarter 2 of 2025 to begin procurement efforts for Acacia Demolition.
April 2022
Past Month’s Accomplishments: No changes.
Next Month’s Milestones: This project is targeted to recommence in Quarter 2 of 2025 to begin procurement efforts for Acacia Demolition.
March 2022
Past Month’s Accomplishments: No changes.
Next Month’s Milestones: This project is targeted to recommence in Quarter 2 of 2025 to begin procurement efforts for Acacia Demolition.
February 2022
Past Month’s Accomplishments: No changes.
Next Month’s Milestones: This project is targeted to recommence in Quarter 2 of 2025 to begin procurement efforts for Acacia Demolition.
January 2022
Past Month’s Accomplishments: The project budget was finalized.
Next Month’s Milestones: This project is targeted to recommence in Quarter 2 of 2025 to begin procurement efforts for Acacia Demolition.
December 2021
Past Month’s Accomplishments: Project is on hold.
Next Month’s Milestones: This project is targeted to recommence in Quarter 2 of 2025 to begin procurement efforts for Acacia Demolition.
November 2021
Past Month’s Accomplishments: The project budget was finalized.
Next Month’s Milestones: This project is targeted to recommence in Quarter 2 of 2025 to begin procurement efforts for Acacia Demolition.
October 2021
Past Month’s Accomplishments: The project schedule and charter were finalized.
Next Month’s Milestones: The project budget will be finalized.
September 2021
Past Month’s Accomplishments: The project schedule was further evaluated based on planned Acacia demolition.
Next Month’s Milestones: The project schedule will be finalized.
August 2021
Past Month’s Accomplishments: Conceptual estimates of various planning and program opportunities were presented to the college. Phase II planning for this project concluded with plans to demolition the Acacia building as an opportunity site for a future Student Activities Center due to cost/scope challenges.
Next Month’s Milestones: The project schedule for Acacia demolition will be further evaluated.
July 2021
Past Month’s Accomplishments: Phase II planning for this project continued due to cost/scope challenges. Conceptual estimates of various planning and program opportunities were received by the Bond Team.
Next Month’s Milestones: Phase II planning for this project continues. The Bond Team will further analyze the conceptual estimates of various planning and program opportunities in preparation of presenting to the College for consideration and feedback.
June 2021
Past Month’s Accomplishments: Phase II planning for this project continued due to cost/scope challenges. Further planning and program opportunities were explored in consideration for the College’s feedback.
Next Month’s Milestones: Phase II planning for this project will continue. The Bond Team will present conceptual estimates of various planning and program opportunities to the college for consideration and feedback.
May 2021
Past Month’s Accomplishments: Phase II planning for this project continued due to cost/scope challenges. Further planning and program opportunities were explored in consideration for the College’s feedback.
Next Month’s Milestones: Phase II planning for this project will continue. The Bond Team will present further planning and program opportunities to the College for consideration and feedback. Planning for procurement efforts will commence.
April 2021
Past Month’s Accomplishments: Phase II planning for this project continued. Planning and program recommendations were presented to the College for consideration and feedback.
Next Month’s Milestones: Phase II planning for this project continues. The Bond Team will begin planning for procurement efforts.
March 2021
Past Month’s Accomplishments: Phase II planning for this project continued due to cost/scope challenges.
Next Month’s Milestones: Phase II planning for this project continues. The project team will meet with the college to present recommendations on next steps and obtain feedback.
February 2021
Past Month’s Accomplishments: Phase II planning for this project continued due to cost/scope challenges as indicated below.
Next Month’s Milestones: Phase II planning for this project continues.
January 2021
Past Month’s Accomplishments: The architectural team finalized the programming report based on the bond team's feedback. The report summarized the findings and recommendations resulting from the programming efforts. Phase 2 planning for this project commenced.
Next Month’s Milestones: Phase 2 planning for this project continues due to cost/scope challenges as indicated below.
December 2020
Past Month’s Accomplishments: The architectural team provided a draft report summarizing the final findings and recommendations resulting from programming efforts.
Next Month’s Milestones: The draft report will be finalized based on feedback provided by the bond team.
November 2020
Past Month’s Accomplishments: The architectural team and the engineer continued investigations on the program to assess how it may fit into the existing building. A preliminary programming cost assessment was prepared to support the findings. The preliminary program was delivered to the Bond Team for review.
Next Month’s Milestones: The architectural team will provide a draft report summarizing the final findings and recommendations resulting from the programming efforts.
October 2020
Past Month’s Accomplishments: JK Architecture and Engineering focused on analyzing the student and user group survey results to develop a preliminary program and test fit of the program. Additionally, a phase one structural assessment was conducted to help better inform the architectural team how to plan for future construction.
Next Month’s Milestones: The architectural team and the engineer will continue investigating the program and how it may fit into the existing building. This will result in a preliminary programming report and cost assessment.
September 2020
Past Month’s Accomplishments: Released user group and student surveys in early September with response period closed in late September. Conducted user group interviews in late September.
Next Month’s Milestones: The architect will analyze student and user group survey results. This will help them develop organizational, adjacencies recommendations as well as develop concept test fit plans.