July 2022
Past Month’s Accomplishments: Project close out was completed.
Next Month’s Milestones: Project is complete.
June 2022
Past Month’s Accomplishments: Punch list and DSA closeout process is in progress.
Next Month’s Milestones: Building sign will be refabricated and its installation will be scheduled. The final stages of the closeout process will begin.
April 2022
Past Month’s Accomplishments: No change.
Next Month’s Milestones: Installation of building identification signage will be completed.
March 2022
Past Month’s Accomplishments: Installation of canopy was completed. Installation of pathway bollards was completed.
Next Month’s Milestones: Building identification signage to be installed.
February 2022
Past Month’s Accomplishments: Installation of the canopy was completed.
Next Month’s Milestones: Building identification signage will be installed along with pathway bollards.
January 2022
Past Month’s Accomplishments: Installation of canopy shade material was completed.
Next Month’s Milestones: Lighting and gutters will be installed.
December 2021
Past Month’s Accomplishments: Welding of structural steel and restoration of the courtyard are complete.
Next Month’s Milestones: Installation of canopy glazing, lighting, and finishes will be completed.
November 2021
Past Month’s Accomplishments: Steel erection was completed. Welding is in progress.
Next Month’s Milestones: Installation of canopy glazing and finishes will be completed.
October 2021
Past Month’s Accomplishments: Footings were poured and curing for the steel installation was completed.
Next Month’s Milestones: Light poles will be installed along Valle del Lago.
September 2021
Past Month’s Accomplishments: Rebar was put in place for footing construction.
Next Month’s Milestones: Concrete pouring and anchor bolt installation will begin. Submission of deferred submittals will be completed.
August 2021
Past Month’s Accomplishments: Site mobilization was completed. Materials and submittal approvals are expected.
Next Month’s Milestones: Site grubbing and concrete work will be completed.
July 2021
Past Month’s Accomplishments: JKL provided construction kick-off documents and has started early submittals.
Next Month’s Milestones: Mobilization to site and start of civil scope.
June 2021
Past Month’s Accomplishments: Four bids were received. JKL Construction provided a low bid.
Next Month’s Milestones: An award is expected at July 2021 Board meeting. The construction kickoff is anticipated to occur in mid-July.
May 2021
Past Month’s Accomplishments: Re-release of solicitation for contractor through public bid. Contract to the July 2021 Board meeting was sent for approval.
Next Month’s Milestones: Receipt of bids and preparation for Board award.
April 2021
Past Month’s Accomplishments: Public bid opportunity.
Next Month’s Milestones: Re-release of solicitation for a contractor through public bid. Contract to the July 2021 Board meeting will be sent for approval.
March 2021
Past Month’s Accomplishments: Outreach for bidders.
Next Month’s Milestones: Procurement of contractor through public bid. Contract to the May 2021 Board meeting for approval.
February 2021
Past Month’s Accomplishments: Approval from DSA.
Next Month’s Milestones: The project will be issued for bidding.
January 2021
Past Month’s Accomplishments: Completed design for DSA backcheck
Next Month’s Milestones: Approval from DSA
December 2020
Past Month’s Accomplishments: Awaiting DSA review comments.
Next Month’s Milestones: Approval of signage package and DSA approval.
November 2020
Past Month’s Accomplishments: Awaiting DSA review comments.
Next Month’s Milestones: Evaluate building identification signage on canopy. Await DSA review comments.
October 2020
Past Month’s Accomplishments: Additional updates to the architectural drawings were incorporated per Division of the State Architect (DSA) comments.
Next Month’s Milestones: Receive Division of the State Architect (DSA) approval.
September 2020
Past Month’s Accomplishments: Updated construction estimates.
Next Month’s Milestones: Anticipated approval from Division of the State Architect (DSA).