Security Hardware
This project focuses on continuing to provide security updates to Evergreen Valley College to support the safety of faculty, administrative staff, and students.
Project Updates
June 2021
Past Month’s Accomplishments: The project was completed on 6/1/2021
Next Month’s Milestones: Project Closeout.
May 2021
Past Month’s Accomplishments: Foster Brothers has completed 98% installation of the locking devices (AD-200). Cedro is remaining.
Next Month’s Milestones: Project Closeout.
April 2021
Past Month’s Accomplishments: Foster Brothers has completed 98% installation of the locking devices (AD-200). Cedro is remaining.
Next Month’s Milestones: Project Closeout.
March 2021
Past Month’s Accomplishments: Foster Brothers has completed 98% installation of the locking devices (AD-200). Cedro is remaining.
Next Month’s Milestones: Project Closeout.
February 2021
Past Month’s Accomplishments: Foster Brothers has completed 98% installation of the locking devices (AD-200) Cedro is remaining.
Next Month’s Milestones: Project Closeout
January 2021
Past Month’s Accomplishments: Foster Brothers has completed 98% installation of the locking devices (AD 200) Cedro is remaining.
Next Month’s Milestones: Project closeout
December 2020
Past Month’s Accomplishments: Foster Brothers has completed 95% installation of the locking devices (AD-200). Cedo is remaining.
Next Month’s Milestones: Project closeout
November 2020
Past Month’s Accomplishments: Foster Brothers has completed 95% installation of the locking devices (AD-200) Cedro is remaining.
Next Month’s Milestones: Project Completion
October 2020
Past Month’s Accomplishments: Foster Brothers completed 90% installation of the locking devices (AD-200). The Cedro building is remaining to be completed as that building is under active construction.
Next Month’s Milestones: Continue to install new locking cores and hardware.
September 2020
Past Month’s Accomplishments: Foster Brothers completed 90% installation of the locking devices (AD-200).
Next Month’s Milestones: Complete installation of cores and the remainder of the AD-200s.