North Fire Lane / ADA

This project is a universal design, ADA access, and fire access improvement project.

View Project Updates

 

The project includes the removal of the existing walkway and all known access barriers on the North Fire Lane. The project will install a new walkway that will double as a fire lane extending from the existing Student Services Building to the Police Station and Sequoia Building. The new pathway will meet local fire jurisdiction access needs. The areas on either side of the path will be developed to include learning environments and water mitigation/runoff beds. Additional campus identification and wayfinding will be provided, and the original water fountain will be replaced.

Construction is projected for completion in Fall 2021.


Project Updates

June 2023

Past Month’s Accomplishments: A Notice of Completion was filed.

Next Month’s Milestones: The project is complete.


May 2023

Past Month’s Accomplishments: Final billing was completed.

Next Month’s Milestones: A Notice of Completion is expected.


April 2023

Past Month’s Accomplishments: Final billing was completed.

Next Month’s Milestones: A Notice of Completion is expected.


March 2023

Past Month’s Accomplishments: Final billing was completed.

Next Month’s Milestones: A Notice of Completion is expected.


February 2023

Past Month’s Accomplishments: Final billing was completed.

Next Month’s Milestones: A Notice of Completion is expected.


January 2023

Past Month’s Accomplishments: Final allowance reconciliation was completed.

Next Month’s Milestones: A Notice of Completion is expected.


December 2022

Past Month’s Accomplishments: Project is complete.

Next Month’s Milestones: Allowance reconciliation expected.


November 2022

Past Month’s Accomplishments: Fire lane installation was completed.

Next Month’s Milestones: Bollard installation will be completed.


October 2022

Past Month’s Accomplishments: Preparation for handrail and bollard installation began.

Next Month’s Milestones: Handrail and bollard installation will be completed.


September 2022

Past Month’s Accomplishments: Handrail shop drawings were approved.

Next Month’s Milestones: Handrails and bollards will be installed.


August 2022

Past Month’s Accomplishments: Ramp, curbs, and associated landscaping were installed.

Next Month’s Milestones: Handrails and bollards will be installed.


July 2022

Past Month’s Accomplishments: Admissions & Records ramp design construction change directive 007 was approved by DSA. Stair demolition was completed.

Next Month’s Milestones: Ramp installation will be completed.


June 2022

Past Month’s Accomplishments: Admissions & Records design construction change directive was drafted for DSA submission. Construction change directive 004 for handrail modification was completed.

Next Month’s Milestones: Construction change directive 007 will be sent for approval.


May 2022

Past Month’s Accomplishments: Admissions & Records ramp design was reviewed.

Next Month’s Milestones: Admissions & Records ramp design will be submitted to DSA as a Construction Change Directive.


April 2022

Past Month’s Accomplishments: Punchlist items were completed.

Next Month’s Milestones: Construction Change Directive 004 handrail will be completed.


March 2022

Past Month’s Accomplishments: The punchlist began.

Next Month’s Milestones: Outstanding punchlist items, such as electrical work, will be addressed.


February 2022

Past Month’s Accomplishments: Fire hydrant replacement was completed. A punch list was created.

Next Month’s Milestones: Shade structure fabric will be installed. The punch list will be completed.


January 2022

Past Month’s Accomplishments: Flatwork, landscaping, lighting were completed for Phase 2B. The shade structure steel was installed. Reduction of the site fence completed.

Next Month’s Milestones: Installation of shade structure fabric, fire hydrant replacement, and punch list items will be completed.


December 2021

Past Month’s Accomplishments: Installation of colored concrete flatwork, landscaping, electrical, and logo sign at Phase 2B were completed, along with the reduction of the site fence.

Next Month’s Milestones: Installation of the final shade structure post and pavers will be completed.


November 2021

Past Month’s Accomplishments: Installation of colored concrete flatwork, landscaping, and electrical were completed. Rough grading and underground utility installation at Phase 2A and 2B were completed, as well as concrete placement at Phase 2A.

Next Month’s Milestones: Concrete placement and landscaping at phase 2A and 2B will be completed.


October 2021

Past Month’s Accomplishments: Installation of colored concrete flatwork, landscaping, and electrical were completed. Rough grading and underground utility installation at Phase 2A and 2B were completed, as well as concrete placement at Phase 2A.

Next Month’s Milestones: Concrete placement and landscaping at phases 2A and 2B will be completed.


September 2021

Past Month’s Accomplishments: Installation of colored concrete flatwork, landscaping, electrical and water feature finishes were all competed. Rough grading and underground utility installation are at Phase 2A. Concrete placement at Phase 2A was started. Demolition and subgrade at Phase 2B were completed.

Next Month’s Milestones: Concrete placement and landscaping at Phase 2A will be completed. Concrete placement at Phase 2B will also be completed.

ABF012C8-8A1F-4103-B2C6-63F0223C6C59.jpeg

August 2021

Past Month’s Accomplishments: Colored concrete flatwork, landscaping, electrical and water feature finishes were all completed. Rough grading and underground utility installation at Phase 2A were also completed.

Next Month’s Milestones: Demolition of Phase 2B will begin. Underground utilities and irrigation at phase 2A will continue.

A441071E-3685-4B72-92BD-2FB8CED2009E.jpeg
484A6342-24C4-4E00-9AE7-4C0392CAA4C7.jpeg

July 2021

Past Month’s Accomplishments: The colored concrete flatwork and water feature finishes were installed. Demolition of Phase 2A existing concrete was completed.

Next Month’s Milestones: Landscaping at Phase 1 and underground utilities and irrigation at phase 2A will be completed.

8395AEF9-178D-43AA-A181-3DC9742306F8.jpeg
867EA689-B8B7-488D-9DBA-B38AC5737B3D.jpeg

June 2021

Past Month’s Accomplishments: Installation of colored concrete flatwork and water feature were completed.

Next Month’s Milestones: Demolition of existing concrete will be completed. Colored concrete flatwork will be installed.


May 2021

Past Month’s Accomplishments: Underground Utilities were installed.

Next Month’s Milestones: Underground utilities and concrete pours are expected to continue.

58166D41-363F-47DD-9909-61F7277FF451.jpeg
B6910F05-4868-4293-B18A-2D05F9FAEBC2.jpeg

April 2021

Past Month’s Accomplishments: Demolition and grading commenced.

Next Month’s Milestones: Underground utilities and concrete pours are expected.

Construction Updates: The current and upcoming work items include the following:

  • Installation of electrical, domestic water, and sanitary sewer

  • Base rock and compaction

  • VPA-B ADA Upgrades

    • Upgrade to new, compliant door actuators

    • Modifications to partitions and restroom accessories to meet ADA code

  • SSC building concrete slab repair

    • Demolition of concrete adjacent to SSC complete

    • Drilling and installing rebar complete

    • Formwork

    • Concrete pour

Construction Updates1.jpg
Construction Updates2.jpg

March 2021

Past Month’s Accomplishments: Site protection measures in place. Demolition and grading commenced.

Next Month’s Milestones: Demolition continues.


February 2021

Past Month’s Accomplishments: Contract award mobilization of contractor.

Next Month’s Milestones: Site protection measures. Demolition and grading.


January 2021

Past Month’s Accomplishments: DSA approval

Next Month’s Milestones: Issue the construction contract.

nfla-01-nov.jpg
nfla-02-nov.jpg

December 2020

Past Month’s Accomplishments: Design has been under DSA review since July. Anticipate DSA approval 11/30.

Next Month’s Milestones: Issue the construction contract.


November 2020

Past Month’s Accomplishments: Design has been under DSA review since July. Anticipate DSA approval 11/30.

Next Month’s Milestones: Issue the construction contract.


October 2020

Past Month’s Accomplishments: Design has been under Division of the State Architect (DSA) review since July. DSA approval is anticipated by October 30, 2020. The Bond Team reviewed project budget and estimates with campus leadership in preparation for bidding the construction project.

Next Month’s Milestones: Finalize the bid process.


September 2020

Past Month’s Accomplishments: Design has been under Division of the State Architect (DSA) review since July. DSA approval is anticipated in October. Team reviewed project budget and estimates.

Next Month’s Milestones: Finalize Division of the State Architect (DSA) review and construction budget. Advertise and release the construction bid.