Campus Wayfinding - Monuments and Badges
Wayfinding is critical to ensure students, faculty, and staff have a positive college experience.
The project will provide 15'-tall, freestanding monument signs at each building. Additionally, secondary wall mounted signs that will be install facing the nearest parking lot. The color of the signs is programmable to match special events on campus or match the new exterior color of the buildings.
Construction is projected for completion in March 2021.
Jump to Month
Project Updates
January 2024
Past Month’s Accomplishments: Final programming is underway. Close-out documentation was completed. A Notice of Completion was sent to the January Board.
Next Month’s Milestones: The project is complete.
December 2023
Past Month’s Accomplishments: Final programming is underway. Close-out documentation was completed.
Next Month’s Milestones: A Notice of Completion will be presented to the January Board.
November 2023
Past Month’s Accomplishments: Final programming is pending. Close-out documentation was completed.
Next Month’s Milestones: Programming completion is expected. A Notice of Completion will be filed in January 2024.
October 2023
Past Month’s Accomplishments: Final programming and testing were completed.
Next Month’s Milestones: Programming completion is anticipated. Close-out completion will be confirmed. A Notice of Completion will be filed in December.
September 2023
Past Month’s Accomplishments: Final programming and testing were completed.
Next Month’s Milestones: Programming will be completion is anticipated. Closeout completion is anticipated. A Notice of Completion will be filed in November.
August 2023
Past Month’s Accomplishments: Closeout continued.
Next Month’s Milestones: Programming will be initiated. Closeout completion is anticipated. A Notice of Completion will be filed in October.
July 2023
Past Month’s Accomplishments: Closeout continued.
Next Month’s Milestones: Programming will be initiated. Closeout completion is anticipated. A Notice of Completion will be filed in September.
June 2023
Past Month’s Accomplishments: Closeout continued.
Next Month’s Milestones: Closeout completion is expected. A Notice of Completion will be filed.
May 2023
Past Month’s Accomplishments: Closeout continued.
Next Month’s Milestones: Closeout completion is expected. A Notice of Completion will be filed.
April 2023
Past Month’s Accomplishments: Installation of new signs and closeout were completed.
Next Month’s Milestones: The project is complete.
March 2023
Past Month’s Accomplishments: Shop fabrication of two new signs was completed.
Next Month’s Milestones: Installation of the new signs will be completed. The close out process will be completed as well.
February 2023
Past Month’s Accomplishments: A change order addition of two new signs was completed. Sign procurement is underway. The final closeout document was received.
Next Month’s Milestones: Shop fabrication of new signs is expected. Installation of new foundation for monument sign will be completed.
January 2023
Past Month’s Accomplishments: A change order addition of two new signs was completed. Sign procurement is underway. The final closeout document was received.
Next Month’s Milestones: Shop fabrication of new signs is expected. Installation of new foundation for monument sign will be completed.
December 2022
Past Month’s Accomplishments: Warranty repairs are underway.
Next Month’s Milestones: Final close-out document approval and Notice of Completion are expected. Project is complete.
November 2022
Past Month’s Accomplishments: Warranty repairs are underway.
Next Month’s Milestones: Final close-out document approval and Notice of Completion are expected. Project is complete.
October 2022
Past Month’s Accomplishments: Warranty repairs are underway.
Next Month’s Milestones: Final close-out document approval and a Notice of Completion is expected. The project is complete.
September 2022
Past Month’s Accomplishments: Punchlist repairs are ongoing.
Next Month’s Milestones: Final close-out document approval and a Notice of Completion are expected.
August 2022
Past Month’s Accomplishments: Punch list repairs are ongoing.
Next Month’s Milestones: Final close-out document approval is expected. A Notice of Completion will be submitted.
July 2022
Past Month’s Accomplishments: Punch list repairs are ongoing.
Next Month’s Milestones: Final close-out document approval is expected. A Notice of Completion will be submitted.
June 2022
Past Month’s Accomplishments: Punch list repairs are ongoing. Program/Controller final connections were completed. All signs were programmed and operational as planned.
Next Month’s Milestones: Punch list repairs will continue.
May 2022
Past Month’s Accomplishments: Punch list repairs are underway. Sequoia, Administration & Records and Acacia signs were repaired. Program/Controller final connections and testing were completed. LED Controller training with District was carried out. All signs are programmed and operational as planned.
Next Month’s Milestones: Punch list repairs will continue. A Program/Controller punch walk will be carried out.
April 2022
Past Month’s Accomplishments: Punchlist repairs are underway. The VPA Plaza monument sign was completed. Programming and LED Controller installation was completed. Program/Controller final connections are underway.
Next Month’s Milestones: Punchlist repairs will continue. Controller program testing and start-up will be completed. Program training with the District will be carried out.
March 2022
Past Month’s Accomplishments: Punch list repairs are underway. VPA Plaza monument sign was completed. Programming/LED controller installation was complete. Program/controller final connections are underway.
Next Month’s Milestones: Punch list repairs will continue. Controller program testing and start up to occur. Program training with the District to be carried out.
February 2022
Past Month’s Accomplishments: A formal punchlist was conducted. A revised repair plan was drafted and approved. An LED program was finalized with the District.
Next Month’s Milestones: Offsite repair work will commence. Signs will be removed per the prescribed plan. Installation of LED controllers inside signs and related wiring inside campus electrical rooms will be completed.
January 2022
Past Month’s Accomplishments: Installation of monument signs was completed. The formal punch list was conducted, and a repair plan was drafted to address finish and acrylic installation inconsistencies. The LED Program was finalized with the District.
Next Month’s Milestones: Punch list work and removal and sign skins and acrylic (offsite) will begin. Sign will be removed per the prescribed plan. Installation of LED controllers inside signs and related wiring inside campus electrical rooms will be completed.
December 2021
Past Month’s Accomplishments: A punch list walk with the contractor was performed. A new lead project manager was assigned by the vendor to assist with work not meeting quality expectations.
Next Month’s Milestones: Monument sign installation, punch list repairs and final programming will be completed.
November 2021
Past Month’s Accomplishments: Installation of wall badge signage was completed and monument sign installation is underway. Installations at VPA plaza, Gullo I and Gullo II have been completed. Shop fabrication is nearing completion. Pre-planning is underway for signage LED programming.
Next Month’s Milestones: Completion of monument sign installation, punch list repairs and final programming is expected. Demonstration of preliminary LED programming has been conducted, with additional programming options under review.
October 2021
Past Month’s Accomplishments: Installation of wall badge signage is underway. VPA A, VPA B, Gullo, Fitness Center, Gymnasium and LETC are complete including related restoration to surrounding areas. Fabrication of monument signage is underway, completion schedule for 10/29/21. Deliveries to site Begin immediately after fabrication, followed by installation. Preplanning underway for signage programming.
Next Month’s Milestones: Completion of wall badge sign installation and commencement of monument installation is expected. Programming schedule will be completed followed by demonstrations.
September 2021
Past Month’s Accomplishments: Site progress has been reinstated with a new contractor team. A new fabrication subcontractor has been approved. The contractor has committed to completing the project with a new schedule and extended completion date. Fabrication is in progress and is being expedited for completion by the end of October.
Next Month’s Milestones: Installation of the initial first few signs will begin and occur throughout the month. Restoration work for interior and exterior surfaces is being coordinated to occur with installation to minimize the impact to the Campus. Programming options and planning will be reviewed and coordinated with the District.
August 2021
Past Month’s Accomplishments: Site progress has been reinstated with a new contractor team. A new fabrication subcontractor has been approved. Contractors have committed to completing the project. Minimal progress has begun, correcting deficiencies, providing materials, and updating the schedule.
Next Month’s Milestones: Shop fabrication to commence with partial delivery of signs scheduled for mid-October. Installation and restoration schedule will be coordinated to reduce impact to the campus.
July 2021
Past Month’s Accomplishments: Site progress has been stopped due to the contractor abandoning the site. A default notice has been issued by the district. No work has progressed.
Next Month’s Milestones: District is seeking to potentially terminate the signage contractor due to inability to meet commitments and satisfy outstanding contractual requirements necessary and complete certification for DSA required Inspections.
June 2021
Past Month’s Accomplishments: Monument sign foundations were completed.
Next Month’s Milestones: The contractor will satisfy outstanding contractual document requirements necessary and complete certification for DSA required inspection to begin shop fabrication of signs.
May 2021
Past Month’s Accomplishments: Investigative review of building wall attachment was performed. Placement of pre-cast concrete bases was set at monument signs. A formal delay notice was issued to the contractor for non-performance related to the manufacturing of the signs.
Next Month’s Milestones: Anticipated completion of sign fabrication and structural wall attachment. Installation of four sign foundations in the North Fire Lane area.
April 2021
Past Month’s Accomplishments: The installation of sign foundation (borings), steel support post installation, and concrete platforms for the signs was completed. A formal delay notice was issued to the contractor for non-performance related to the manufacturing of the signs.
Next Month’s Milestones: Anticipated completion of sign fabrication, structural wall attachment. Installation of four sign foundations in the North Fire Lane area.
March 2021
Past Month’s Accomplishments: Completion of all electrical & data rough-in and site restoration. Commencement of sign foundation (borings).
Next Month’s Milestones: Completion of sign foundation borings and structural installation. Shop fabrication underway for signage contractor.
February 2021
Past Month’s Accomplishments: Completion of electrical & data rough-in and trench repair work at Fitness Center, Gullo & Gullo 2. DSA approval for signs now complete.
Next Month’s Milestones: Completion of VPA Plaza electrical and data work, restoration of site by Electrical contractor. Commencement of foundations for Monument signage. Mockup #2 review of substitution LED fixtures proposed by sign contractor.
January 2021
Past Month’s Accomplishments: Completion of electrical & data rough in and trench repair work at Fitness Center, MS3, PE/Gymnasium areas. Mockup and lighting demonstration for signs conducted. Redlines drawings received from DSA, correction underway.
Next Month’s Milestones: DSA approval anticipated. Completion of Gullo and VPA Plaza electrical and data work. DSA back check / approval of sign shop drawings anticipated.
December 2020
Past Month’s Accomplishments: Design is 100% complete, overall project is 40% complete.
Next Month’s Milestones: Completion of electrical and data rough in and trench repair.
November 2020
Past Month’s Accomplishments: Completion of electrical & data rough-in and trench repair work at Student Services, Acacia, Admin & Records. Revision of Shop Drawings for resubmission to DSA.
Next Month’s Milestones: Continued power and data rough-in work at interior and exterior locations at Fitness Center, Physical Education, Gymnasium and MS3.DSA project upload 12/1/20.
October 2020
Past Month’s Accomplishments: Completed Auto Tech, LETC, and Cedro buildings power and data rough-ins. Restored hardscape to existing conditions.
Next Month’s Milestones: Continued power and data rough-in work at interior and exterior locations at Sequoia, Student Services, Admin & Records and Acacia. It is required to resubmit drawings to the Division of the State Architect (DSA) in December.
September 2020
Past Month’s Accomplishments: Complete the site survey of existing conditions in coordination with planned sign locations. Power and data rough-in work at interior and exterior locations for Sequoia, Auto Tech and Cedro continued.
Next Month’s Milestones: Continue power and data rough-ins, commencement of monument sign foundation layout and site preparation. Division of the State Architect (DSA) approval anticipated between late October and mid-November.