Campus-Wide Signage

This project will respond holistically to new construction, renovation, and site improvement efforts funded by the Measure X Bond Programs on the Evergreen Valley College campus.

View Project Updates

 

Project outcomes include promoting accessibility on campus by providing strong and intuitive wayfinding solutions for Students and Visitors in coordination with the campus accessibility transition plan, promoting the safety and well-being of students on campus by reassigning existing parking lot numbers with enhanced logical sequencing to promote clear communication with Campus Police Department, and application of a cohesive sign program across campus.



Project Updates

August 2024

Past Month’s Accomplishments: Phase II / III: Site and schedule coordination continued. Additional signage procurement and pole-mounted flag installation were completed.

Next Month’s Milestones: Phase II/III: Monument scheduling will begin. The remaining installations will be completed.


July 2024

Past Month’s Accomplishments: Phase II / III: Site and schedule coordination continued. Punch list work is ongoing. Additional signage procurement was completed.

Next Month’s Milestones: Phase II/III: Pole-mounted flag installation will be completed. Monument scheduling will begin.


June 2024

Past Month’s Accomplishments: Phase II / III: Interior signage was installed at the Visual and Performing Arts and Acacia buildings, and signage layout and coordination in the Fitness, Gym, and LETC buildings was completed. Site and schedule coordination is ongoing.

Next Month’s Milestones: Phase II/III: Signage at the MS3, Autotech, Gullo I, and Gullo II will be installed. The monument signage scope will be awarded, and shop drawings and samples are expected to be approved.


May 2024

Past Month’s Accomplishments: Phase II / III: Interior signage was installed at the Visual and Performing Arts and Acacia buildings, and signage layout and coordination in the Fitness, Gym, and LETC buildings was completed. Site and schedule coordination is ongoing.

Next Month’s Milestones: Phase II/III: Signage at the MS3, Autotech, Gullo I, and Gullo II will be installed. Award of the monument signage scope and approval of shop drawings and samples are expected.


April 2024

Past Month’s Accomplishments: Phase II / III: Schedule coordination is ongoing. The signage at the Visual and Performing Arts building was installed.

Next Month’s Milestones: Phase II/III: Installations at the Fitness Center, PE/Gym, and the LETC buildings will be completed. An award of the monument sign scope is expected.


March 2024

Past Month’s Accomplishments: Phase II / III: Submittals and shop drawings were completed. Schedule coordination is ongoing and fabrication is underway.

Next Month’s Milestones: Phase II/III: VA and PA installations are scheduled. Campus schedule coordination will continue. An award of the monument sign scope is expected.


February 2024

Past Month’s Accomplishments: Phase II / III: A contract was issued, and procurement is underway. Shop drawings are in review. Schedule coordination was completed.

Next Month’s Milestones: Phase II/III: Submittals, product sample reviews, and installation schedule approval are anticipated.


January 2024

Past Month’s Accomplishments: Phase II / III: The project contract was issued, and procurement is underway. Shop drawings are in review. Schedule coordination was completed.

Next Month’s Milestones: Phase II/III: Submittals, product sample reviews, and installation schedule approval are expected.


December 2023

Past Month’s Accomplishments: Phase II / III: A contract was issued and procurement is underway.

Next Month’s Milestones: Phase II/III: Submittals and product sample reviews are expected, along with installation schedule approval.


November 2023

Past Month’s Accomplishments: Phase II / III: Project bids were received. A Notice of Intent to Award was presented to the November Board.

Next Month’s Milestones: Phase II/III: Notice to Proceed issuance is expected for December, followed by the commencement of contract procurement. A preliminary construction schedule review is expected for January.


October 2023

Past Month’s Accomplishments: Phases II and III: Project bids were received. A Notice of Intent to Award was prepared for the November Board meeting. A Notice to Proceed was prepared for November 15, 2023.

Next Month’s Milestones: Phases II and III: The Notice to Proceed will be issued. Contract procurement is anticipated. A preliminary construction schedule will be reviewed.


September 2023

Past Month’s Accomplishments: Phases II and III: Project re-bid is underway. The project is being re-bid as two projects, combined into a single project, with two scopes of work and separate pricing. The mandatory bid walk and review meeting were completed. Addendums are being issued to address questions.

Next Month’s Milestones: Phases II and III: Bids are due 10/17/2023 at 2 p.m. The apparent successful contractor will be reviewed post-bid, and a Notice of Intent to Award is anticipated. The Board review will be in November.


August 2023

Past Month’s Accomplishments: Phase II: The contractor was terminated for non-performance. Re-bid documents were prepared and completed. Public advertisement and bid notification were published. Emergency ADA signage was installed. Phase III: Bid documents were published with Phase II. The projects will be bid together but as separate projects. A mandatory bid walk was completed, with bid addendums anticipated.

Next Month’s Milestones: Phase II: Bid activities will continue. Phase III: Bid activities will continue.


July 2023

Past Month’s Accomplishments: Phase II: Preparation for re-bidding is underway due to the termination of the phase II contractor. Phase III: Design was completed. Re-bidding is underway, and phase III will be added to the phase II bid as separate scope and pricing.

Next Month’s Milestones: Phase II: Bidding activities will continue. Phase III: Bidding activities will continue.


June 2023

Past Month’s Accomplishments: Phase I: The project was completed. Phase II: Material procurement is ongoing. Site preparation is underway for monument signage. Interior sign installation was scheduled for mid to late July. Phase III: Design was completed. Bid advertisement was issued. Preparation of design and bid documentation is underway. A public-private partnership (P3) bid walk was scheduled for late July.

Next Month’s Milestones: Phase I: Allowance reconciliation is expected. Phase II: Visual Arts and Performing Arts signage installation will be completed. Monument signage is expected to be completed. Phase III: 100% of the construction drawing plans and specifications will be completed.


May 2023

Past Month’s Accomplishments: Phase I: A punch list correction review was completed. Phase II: Material procurement is ongoing. Layout preparation is underway for the Parking Lot 6 monument sign. Phase III: The Wayfinding Strategy and remaining open design item review meeting was rescheduled to May due to conflicts with the College's availability. Ross +Luthin continued to develop the construction documentation set.

Next Month’s Milestones: Phase I: Closeout is expected. Phase II: Visual Arts and Performing Arts signage installation will commence. Monument signage will be completed. Phase III: A complete review of 100% CD plans will be carried out.


April 2023

Past Month’s Accomplishments: Phase I: Punch list correction is outstanding. Phase II: Material procurement and reviews are underway. Phase III: The wayfinding strategy and remaining open design item review meeting was rescheduled to May due to conflicts with the College's availability. Ross+Luthin continued to develop the construction documentation set.

Next Month’s Milestones: Phase I: Closeout will begin. Phase II: Parking Lot 6 monument sign installation and planning are underway. Work schedule to commence in mid-May 2023. Phase III: The design team will meet with the College to present the proposed wayfinding strategies and remaining open design items. Ross+Luthin will continue to develop the construction documentation set.


March 2023

Past Month’s Accomplishments: Phase I: Punch list correction was completed. Phase II: Material and submittal reviews and color reviews are underway. Phase III: The bond team provided comments on the design development set submitted by Ross+Luthin.

Next Month’s Milestones: Phase I: The close out process will begin. Phase II: Parking Lot 6 monument sign installation is scheduled to commence in late April 2023. Phase III: The design team will meet with the College to present the proposed wayfinding strategies and remaining open design items.


February 2023

Past Month’s Accomplishments: Phase I: Punch list is underway. Phase II: Design was completed. Project bids were received, and a NOIA was issued. Phase III: The bond team provided comments on the design development set submitted by Ross+Luthin. Phase III: 50% of construction drawing and cost estimate were received.

Next Month’s Milestones: Phase I: Directory vinyl and punch walk will be completed. Phase II: A Notice to Proceed is anticipated, contract procurement is planned. Submittals and samples will begin. Phase III: The design team will meet with the College to present the proposed wayfinding strategies and remaining open design items.


January 2023

Past Month’s Accomplishments: Phase I: Vinyl directories were installed. The punch list is forthcoming. Phase II: Design was completed. Project bids were received, and the NOIA was issued. Phase III: Ross+Luthin Creative submitted the design development set to the bond team for review.

Next Month’s Milestones: Phase I: Directory vinyl and punch walk will be completed. Phase II: The Notice to Proceed is anticipated, and the contract procurement is planned. Phase III: The bond team will review and provide comments on the design development set submitted by Ross+Luthin Creative.


December 2022

Past Month’s Accomplishments: Phase I: All samples were approved. Phase II: Construction procurement efforts to commence December 2022. Phase III: Bond team comments on the schematic design set were returned to Ross+Luthin Creative.

Next Month’s Milestones: Phase I: Directory vinyl and punch walk are expected. Phase II: Construction procurement efforts will commence in December 2022. Phase III: Ross+Luthin Creative will submit the design development set.


November 2022

Past Month’s Accomplishments: Phase I: Vehicular signage installation was completed. Phase II: Construction procurement efforts to commence December 2022. Phase III: Ross+Luthin submitted the schematic design set to the College for review and initial marketing banner designs were presented to the College.

Next Month’s Milestones: Phase I: Directory vinyl and punch walk are expected. Phase II: Construction procurement efforts will commence in December 2022. Phase III: The project team will review the schematic design set.


October 2022

Past Month’s Accomplishments: Phase I: Vehicular signage installation was completed. Phase II: The final revised 100% construction documentation set was submitted to the bond team for final review and sign-off. Ross+Luthin Creative received a Design Notice to Proceed into Design Package #3. Phase III: Ross+Luthin continued site surveys and data analysis of findings.

Next Month’s Milestones: Phase I: Directory vinyl and punch walk will be completed. Phase II: Construction procurement efforts will commence in December 2022. Phase III: Ross+Luthin will conclude site walks and data analyzation efforts. The schematic design set will be submitted to the College for review.


September 2022

Past Month’s Accomplishments: Phase I: Wayfinding and identification signage installation was completed. Phase II: Ross+Luthin submitted the revised 100% construction documentation set. Comments were returned to Ross+Luthin by the College. Phase III: The Phase Initiation meeting took place to formally kick-off Plan/Survey activities. Site surveys began.

Next Month’s Milestones: Phase I: Directory vinyl and punch walk will be completed. Phase II: The final revised 100% construction documentation set will be submitted to the bond team for final review and sign-off. Ross+Luthin Creative will receive a Design Notice to Proceed into Design Package #3. Phase III: Ross+Luthin will continue site survey activities and data analyzation.


August 2022

Past Month’s Accomplishments: Phase I: Wayfinding and identification signage installation was completed. Phase II: Feedback was returned on the 100% construction documentation set.

Next Month’s Milestones: Phase I: Directory vinyl and punch walk will be completed. Phase II: The revised 100% construction documentation set will be submitted to the bond team for final review and sign off. Ross+Luthin Creative will receive a Design Notice to Proceed into Design Package #3. Phase III: Phase Initiation meeting will take place to formally kick off Design Package #3 planning and surveying activities.


July 2022

Past Month’s Accomplishments: Phase I: Wayfinding and identification signage installation was completed. Phase II: Feedback was returned on the 50% Construction Documentation set.

Next Month’s Milestones: Phase I: Directory vinyl and punch walk will be completed. Phase II: The 100% construction documentation set will be submitted to the Bond Team for final review and sign off. Ross+Luthin Creative will receive a Design Notice to Proceed into Design Package #3. Phase III: Phase initiation meeting will take place to formally kick off Design Package #3 planning and surveying activities.


June 2022

Past Month’s Accomplishments: Phase I: Parking lot 4/5 signage installation was completed. Phase II: Ross+Luthin Creative submitted the 50% construction documentation set. Final design concepts were approved by the College.

Next Month’s Milestones: Phase I: Wayfinding and identification signage installation will be completed. Phase II: Feedback will be returned on the 50% construction documentation set. The 100% construction documentation set will be submitted to the bond team for review.


May 2022

Past Month’s Accomplishments: Phase I: Shop drawings were reviewed and approved. Phase II: Ross+Luthin Creative submitted the design development set and design concepts to the bond team for review.

Next Month’s Milestones: Phase I: Parking lot 4/5 signage installation will be completed. Phase II: Feedback will be returned on the design development set. Design concepts for new sign types will be presented to the College for review.


April 2022

Past Month’s Accomplishments: Phase I: Contract was awarded to A Good Sign and Graphics. NTP provided 4/22/2022. Phase II: Ross+Luthin Creative submitted the schematic design set and comments were returned.

Next Month’s Milestones: Phase I: Submittals and review will be completed. Phase II: The design development set will be submitted for review. Concepts for new sign types will be presented to the College for review.


March 2022

Past Month’s Accomplishments: Ross+Luthin Creative submitted the Phase I 100% Construction Documentation set for release in the final addenda for bidders. The Phase I bid period closed on PlanetBids. Ross+Luthin Creative kicked off Phase II of the project with the project team and began survey efforts.

Next Month’s Milestones: Ross+Luthin Creative will assist with Phase I Construction Administration efforts and submit the Phase II Schematic Design set for review. The Board of Trustees will review the Phase I construction contract for approval.


February 2022

Past Month’s Accomplishments: Ross+Luthin Creative submitted the Phase I –95% Construction Documentation set for final review. The Bid Posting was released on PlanetBids.

Next Month’s Milestones: Ross+Luthin Creative will submit the Phase I 100% construction documentation set to release in the final bid addenda. The virtual bid walk will be held and bids will be due. Phase II scope of work will commence.